By Alvaro Flores & Amadou Bah,

In 2013, funding was approved to replace the whole Patterson High School building with a brand new one, but little progress has been made since that time. Patterson High School has a poor facility condition which means that the school is pretty run-down and is now getting worn out. The Patterson Press decided to investigate the reason for this delay and discover what the plan is for the new building.

Back in 2013 a bill was passed and the General Assembly agreed on a financing plan to allow Baltimore to spend roughly $1 billion dollars on school construction to repair or replace broken-down buildings over the next seven years. The plan is known as the 21st Century Buildings fund. The plan requires Baltimore, the city school system, and the state to put up $20 million a year each to help pay back this loan over the next 30 yearsPatterson High School is among the schools scheduled to benefit from this money.

The Patterson High School building is currently 303,582 square feet. The original building was built in 1960 at 230,000 square feet. Additions were built in 1968 with 49,634 square feet and in 1977 with 23,948 square feet. In 1977, a 9,211 square feet renovation was completed. Science lab renovations of 10,800 square feet were completed in 1995 and locker room renovations of 9,225 square feet were completed in 2001. This means that in previous years, instead of building a new school building, they were adding more space to the school.

Not only are we going to get a new building in the near future, we are also going to be pairing up with a Special Education school called Claremont Middle/High School. Also, there are some really special features planned for the new school, such as three additional basketball courts, two additional tennis courts, bleachers for visiting teams, a press box and scoreboards for baseball and softball fields.

According to Jessica Clark, “In 2013 the Government Association approved for the construction of the new Patterson building to occur and will be complete in 2019.” This proves that the new Patterson building is guaranteed, but no updates have been made since that time. The Class of 2017 seniors were all wondering why they won’t see the new building before they leave. It’s coming, Seniors! You’ll just have to come back as alumni.

Patterson High School’s program contains several education programs which will impact the design of the building and the space requirements. These programs are: AOP program, Life Skills, Academy of Engineering / Project Lead the Way / Design Technology, Advertising and Graphic Design, Allied Health, Emergency Medical Technician / Homeland Security, Business Administration / Finance and Accounting, Cosmetic Services, Child Care, and ROTC.

The new building has been delayed for a number of reasons, including disagreements about how to spend the money that has been allocated for the new school (for example: we currently have a pool but a new pool will cost millions of dollars that could otherwise be spent on technology or other things). With that being said, the plan is finally moving forward. Construction on the new building will start this year. It is expected to be finished in the school year 2020-2021. This will be the 3rd Patterson High School building. This new school building will be the future.

 

Enrollment projection:

Source: http://baltimore21stcenturyschools.org/schools/104

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s